Radisson Admiral Plaza Hotel

Radisson Admiral Achieved

36% Reduction in Natural Gas Consumption
Exterior of Radisson Admiral Plaza Hotel

Services Provided

  • Energy Audit
  • Engineering Design, Drawings & Specifications for Energy Retrofit
  • Applications for Financial Incentive
  • Project Management, including Tendering & Contract Administration
  • Commissioning
  • Monitoring & Verification of Energy Savings

Energy Efficiency Measures Implemented

The following measures were implemented:

  • High Efficiency Heating Boiler Retrofit
  • Instantaneous Indirect Water Heaters for DHW and Elimination of DHW Storage Tank
  • DHW Preheat With Make-up Air in Summer
  • Fluid Cooler Loop By Pass in Winter Months
  • Controls for Common Area Make-up Air Unit, Electric Baseboards and Heat Pumps
  • Pool Heat Exchanger Heating Valve & Refrigeration Equipment Water Control Valve Repairs

Close This Window

MTCC#1377 - The Boulevard

MTCC#1377 Achieved

24% Reduction in Overall Energy Costs
Exterior of MTCC#1377 The Boulevard

Services Provided

  • Energy Audit
  • Engineering Design, Drawings & Specifications for Energy Retrofit
  • Applications for Financial Incentive
  • Project Management, including Tendering & Contract Administration
  • Commissioning
  • Monitoring & Verification of Energy Savings

Energy Efficiency Measures Implemented

The following measures were implemented:

  • VFD's on the Make-up Air Units
  • Conversion of Make-up Air Units to Glycol Heating and Cooling System
  • Conversion of DX Cooling for Make-up air units to Chilled Water Switch Over System*
  • High Efficiency Heating Boiler Acting as a Lead Boiler - Heating System
  • High Efficiency Condensing Boiler Acting as a Lead Boiler - DHW System
  • Carbon Monoxide (CO) System to Control Exhaust Fans in the Parking Garage
  • VFD on Domestic Cold Water Booster Pumps
  • VFD on Cooling Tower Fan Motor
  • Upgrade of the existing Building Automation System
  • Whirlpool and Swimming Pool Covers
  • Lighting Retrofit

Close This Window

MTCC#792 - Dynasty Towers

MTCC#792 Achieved

18% Reduction in Overall Energy Costs
Exterior of MTCC#792 Dynasty Towers

Services Provided

  • Energy Audit
  • Engineering Design, Drawings & Specifications for Energy Retrofit
  • Applications for Financial Incentive
  • Project Management, including Tendering & Contract Administration
  • Commissioning
  • Monitoring & Verification of Energy Savings

Energy Efficiency Measures Implemented

The following measures were implemented:

  • Replaced Gas Fired Sections in Make-Up Air Units with Glycol Heating Coils
  • DDC Building Automation System
  • Cover for the Swimming Pool
  • VFD on the Cooling Tower Fan
  • Lighting Retrofit
  • Low-flow Showerheads in the Change Rooms
  • CO System to Control the Parking Garage Exhaust Fans

Close This Window

York Region Administrative Building

York Region Admin. Building Achieved

35% Reduction in Natural Gas Consumption

&

17% Reduction in Electricity Consumption
Exterior of York Region Admin Building

Services Provided

  • Engineering Design, Drawings & Specifications for Energy Retrofit
  • Applications for Financial Incentive
  • Project Management, including Tendering & Contract Administration
  • Construction Management
  • Commissioning
  • Monitoring & Verification of Energy Savings

Energy Efficiency Measures Implemented

The following measures were implemented:

  • Heating Boiler Replacement
  • VFD Air Handling Units Control
  • Chilled Water Pumps VFD Control
  • Hot Water Pumps VFD Control
  • Atrium Return Fans Retrofit
  • Building Lighting Retrofit
  • Committee Rooms Re-Design
  • Washrooms Occupancy Lighting Control
  • Offices Occupancy Lighting Control
  • Atrium Daylighting Control